An imported naval spare becomes an approved indigenised item through five stages: the Navy or a shipyard lists it, on SRIJAN or a Positive Indigenisation List; a vendor develops a sample against that requirement; the naval quality directorate approves the drawings and test plan; the sample is inspected and qualified; and the order that follows can carry assured quantities for up to five years.
- Topic
- Indigenisation and Make in India
- Checked
- 23 September 2026
- Sources
- 5
- Questions
- 5
01
Step one: the item is listed
The Navy and defence shipyards publish items they want indigenised on the SRIJAN portal, and the sixth Positive Indigenisation List, notified 18 August 2026, named 16 items specifically for the Indian Coast Guard alongside 389 DPSU items. A vendor tracking naval opportunities should read both: SRIJAN carries the working Expression of Interest or RFP, while a Positive Indigenisation List signals which items will stop being imported once a qualified Indian source exists.
02
Step two: sample, drawings and development
Where drawings were never transferred with the original import, the vendor works from a physical sample: measuring it, identifying its material by positive material identification, and producing the drawings and process that the original design implies. That technical package, not the sample itself, is what goes forward for approval.
03
Step three: the naval quality directorate approves and inspects
DQA(N), the Directorate of Quality Assurance (Naval), carries out quality assurance for electrical, electronics and weapon equipment and naval stores procured by the Navy, the Coast Guard and shipyards; DQA(WP) covers marine engineering and hull machinery on the same basis. Approving drawings for machinery and spares on order, approving the quality assurance plan, and running inspection and factory acceptance trials against that approved plan are listed among these directorates' functions. A first production sample is typically checked in full against every drawing characteristic before the indigenised spare is accepted for series supply.
04
Step four: the order, once the sample is accepted
DPM 2025 provides for assured orders running up to five years and beyond for items developed under indigenisation by public or private players, with liquidated damages on such contracts capped at 0.1 percent per week rather than the 0.5 percent per week that applies elsewhere. DPSUs and the Coast Guard place these orders through their own Make procedures or in-house development routes, with the exact quantity and term set case by case in the resulting contract, not by a standard formula.
Asked next
Questions people also ask
How does a naval spare go from sample to an approved indigenised item?
Where does an indigenisation project for a naval spare actually start?
Most start with a listing: the Navy, a shipyard or a DPSU publishes the item on the SRIJAN portal, or it appears on a Positive Indigenisation List with an indicative timeline for indigenisation. A vendor responds to the Expression of Interest or RFP that the listing organisation publishes on its own website, not to SRIJAN directly, and begins development from there.
Who inspects and approves an indigenised naval spare?
For electrical, electronics and weapon equipment and naval stores, DQA(N) is the naval directorate responsible; for marine engineering and hull machinery, DQA(WP) covers the same ground. Both approve the drawings and quality assurance plan for the item, then run inspection and factory acceptance trials against that approved plan before the spare is accepted, whichever directorate the purchase order names.
Does the Coast Guard go through the same approval route as the Navy?
Yes. DQA(N)'s charter explicitly covers stores procured by the Navy, the Coast Guard and shipyards, and the sixth Positive Indigenisation List, notified 18 August 2026, listed 16 items specifically for the Indian Coast Guard within the same 405-item notification that covered 389 DPSU items. A Coast Guard indigenisation project follows the same DQA(N) quality assurance route as a Navy one.
What happens between a sample being accepted and an actual order?
Once a sample passes inspection against the approved quality assurance plan, procurement moves from the import route to the qualified Indian vendor. DPM 2025 allows assured orders running up to five years and beyond for items developed under indigenisation, with liquidated damages on such contracts capped at 0.1 percent per week. The specific quantity and term are set in the individual contract, not fixed by policy.
Is a drawing always available to start from, or is reverse engineering normal?
Reverse engineering from a physical sample is common precisely because drawings for an old import were often never transferred. The vendor measures the sample, identifies its material and reconstructs the drawing and process the design implies, and that technical package, rather than the sample, is what the naval quality directorate reviews and approves before production begins.
Checked against
Sources
- 01Sixth Positive Indigenisation List and SRIJAN update, Press Information Bureau, Ministry of Defence
- 02DQA(N): Directorate of Quality Assurance (Naval), Directorate General of Quality Assurance, Ministry of Defence
- 03DQA(WP): Directorate of Quality Assurance (Warship Projects), Directorate General of Quality Assurance, Ministry of Defence
- 04Directorate of Quality Assurance (Naval), Indian Navy
- 05DPM 2025: assured orders and liquidated damages for indigenisation contracts, Press Information Bureau, Ministry of Defence
This guide explains how the system works in general, as the documents above describe it, and was last checked on 23 September 2026. Rules and thresholds change: the governing document is the authority, not this page.
On this site
Where this meets the work
- How indigenisation works here
- The indigenisation service
- The two type approvals on record
- Defence contract works
More in Indigenisation and Make in India
- What is the SRIJAN portal and how do vendors use it?
- What is a Positive Indigenisation List, and what is in the sixth list?
- How do iDEX, DISC and ADITI fund defence startups and MSMEs?
- What is the Technology Development Fund, and who can apply?
- What is the Make-II procedure, and how does it differ from Make-I?
- How is an obsolete spare reverse engineered and qualified?